United States Postal Service – Co-Op
City Station - Bronx, NY
|
|
Photo:
|
Description:
|
|
Photo #1: This is a photo of the completed parking lot prior to
the public opening.
This 70,000+SF parking lot
reconstruction included new site drainage, larger and improved customer
parking, new fences and gates, and a new customer entrance.
|
|
Photo #2: A photo of the customer entrance, including a new USPS sign.
|
|
Photo #3: The Original Site
The photo is of the existing parking lot area prior to
restoration.
|
New Gymnasium - Bronx, NY
|
|
Photo:
|
Description:
|
|
Photo: Opening Day at New
Gymnasium of The South Bronx Job Corp.
|
|
Photo: A view of the gym interior.
The basketball court was the center stage of the opening celebration.
|
|
Photo: A packed entrance on Opening Day
|
|
Photo: A photo from the adjacent bldg. looking Southeast
This overview of the new 9,000+ s.f. gymnasium shows the
progress to date. The steel barrel truss roof can be seen. The
rooftop mechanical units are being lowered into place on the left of the
photo.
|
|
Photo: A photo looking South describes the entire site.
The lower structure contains the offices, workout rooms,
and kitchen. The gymnasium is under the metal roof.
|
|
Photo: A photo of the steel barrel truss roof.
The photo is of the interior of the gymnasium. The steel truss
roof structure and the metal roof panels are visible. The exterior
walls are a combination of typical CMU and acoustical CMU to minimize
acoustical effects.
|
Panorama Flight
Services - White Plains,
NY
|
|
Photo:
|
Description:
|
|
Photo #1: An aerial photo overlooking the entire complex
Agency Construction built the 30,000 s.f. main hangar
shown on the left. The open door provides a 100 ft. clear span to
maximize useable space.
Agency also performed all survey, foundation, and electrical
work for the each of the airplane storage buildings in the
background.
|
|
Photo #2: A photo of the concrete foundation walls for the
below-grade fire suppression system.
|
|
Photo #3: A photo of the finished interior hangar space.
Due to poor soil conditions, the concrete slab was
reinforced to support the weight of the planes.
The structural steel frames include tapered sections to
maximize steel efficiency and provide a 200 ft. clear span for maximum
useable space.
|
Northport VA Chiller
Replacement - Northport,
NY
|
|
Photo:
|
Description:
|
|
Photo #1: A photo of the cooling towers air-lifted in place by
helicopter.
Due to the location of the new cooling towers on the existing roof, a
helicopter was required to air lift them into place. A crane was not
a feasible alternative.
|
|
Photo #2: A photo of the cooling tower being lowered into place on
the roof.
|
|
Photo #3: A photo of the interior piping for the new chillers.
|
Northport VA Psychiatric
Ward - Northport, NY
|
|
Photo:
|
Description:
|
|
Photo #1: A photo of a portion of the finished interior.
|
|
Photo #3: A photo of the interior hallway.
|
|
Photo #2: A photo of the HVAC unit outside the structure.
|
St. Albans
Upgrade Wards B2 and B3 - Queens,
NY
|
|
Photo:
|
Description:
|
|
Photo #1: A photo of the rooftop HVAC unit.
|
|
Photo #3: A photo of the HVAC rooftop unit being lowered into
place by a crane.
|
Miscellaneous Notable Projects of Interest
|
|
Bronx
VA Therapeutic Pool
|
Dunkin’ Donuts, 42nd St. and 9th Ave, New York, NY
|
Brooklyn VA District Council Building;
Brooklyn, NY: Pile Caps and Foundation
|
The Tappan Post
Office; Tappan, NY was constructed by Agency Construction Corp.
|
|
|
|
|